See What You Get

Sample outputs from Monte Carlo risk analysis. Charts, summaries, and downloadable reports.

📅

Schedule Risk Analysis

Finish date confidence, task sensitivity, and schedule contingency

Summary Dashboard

Plan Finish
Jun 15, 2025
P50 Finish
Jul 2, 2025
+17 days
P80 Finish
Jul 18, 2025
+33 days
P90 Finish
Jul 29, 2025
+44 days

Distribution Analysis

Finish Date Distribution
P50
P80
P90
Jun 15 Jul 1 Jul 15 Aug 1
Confidence Curve (S-Curve)
90%
80%
50%
P50: Jul 2
P80: Jul 18
Jun 15 Jul 1 Jul 15 Aug 1

Sensitivity Analysis

Duration Uncertainty - Top Drivers
Development Phase 2
18 days
Integration Testing
14 days
Development Phase 1
12 days
Design & Architecture
8 days
Requirements
6 days
💵

Cost Risk Analysis

Budget confidence, contingency calculation, and cost drivers

Summary Dashboard

Baseline
$485,000
P50 Cost
$512,000
+$27K (+5.6%)
P80 Cost
$568,000
+$83K (+17.1%)
P90 Cost
$612,000
+$127K (+26.2%)

Distribution & Breakdown

Total Cost Distribution
Base
P50
P80
P90
$450K $500K $550K $650K
Cost by Category
Labor
$248K - $350K
Equipment
$85K - $122K
Materials
$68K - $92K
Services
$45K - $68K
Baseline P50 P90

Cost Drivers

Cost Uncertainty - Top Drivers
Development Team
$65K
Infrastructure
$40K
QA & Testing
$30K
Project Management
$25K
Software Licenses
$15K
🔗

Integrated Risk Analysis

Combined schedule and cost with correlation and cash flow

Combined Summary

📅 Schedule

Plan Jun 15
P50 Jul 2
P80 Jul 18
P90 Jul 29

💵 Cost

Base $485K
P50 $512K
P80 $568K
P90 $612K

Cost-Schedule Correlation

Cost vs Schedule Scatter Plot
Total Cost
Days from Plan
Sched P50
Sched P90
Cost P50
Cost P90
0 +15 +30 +45 days
Correlation: 0.72 - Schedule delays strongly correlate with cost increases

Cash Flow Analysis

Monthly Cost Burn-down
Mar
Apr
May
Jun
Jul
Aug
P50 P90
Cumulative Cost Curve
P90: $612K
P50: $512K
Mar Apr May Jun Jul
📥

Downloadable Reports

Comprehensive Excel reports with all analysis data

📅 Schedule Risk Report

Summary
Task Results
Risks
Statistics
SCHEDULE RISK ANALYSIS
Plan Finish:Jun 15, 2025
P50 Finish:Jul 2, 2025
P80 Finish:Jul 18, 2025
P90 Finish:Jul 29, 2025
Schedule Contingency (P80):+33 days
Tasks Analyzed:24
Risks Included:8
Simulations:5,000

Report Contains:

  • Summary with P-values
  • Task-level finish dates
  • Risk register analysis
  • Simulation statistics
  • Raw simulation data

💵 Cost Risk Report

Summary
Cost Items
Categories
Risks
COST RISK ANALYSIS
Baseline Cost:$485,000
P50 Cost:$512,000
P80 Cost:$568,000
P90 Cost:$612,000
Contingency (P80):$83,000 (17.1%)
Items Analyzed:18
Categories:5
Simulations:5,000

Report Contains:

  • Summary with contingency %
  • Item-level P50/P90 costs
  • Category breakdown
  • Risk register analysis
  • Simulation statistics